October 22, 2013

Expected St. Louis Build Out Schedule

Everything is always subject to change, sure, but here is our plan.

Week of 10/21 - Contractor Finish
Week of 10/28 - Brentwood Inspections
Week of 11/4   - Drywall and Paint Finish
Week of 11/11 - Floor and Rig Construction, Shelving, Desk, Setup
Week of 11/18 - LIVE!

This has been a long time coming and we appreciate everyone's patience with crowding as we worked to finish this space. Just a month more and we should see an amazing new space in action!